Case Study: Compression Facility Design

Marcellus Shale

 
Project at a Glance

Location

Morgantown, WV

Project Type:

Turn‐key compression and dehydration

Challenges Identified

  • Vintage equipment
  • Redesigned plot plans
  • Land restrictions
  • Reduction in site space
Results No delays in startups due to any challenges.

Project Overview

Our client sought GCC’s services with an objective to design and install a turn‐key compression and dehydration service. The installation included (10) 1680HP Waukesha 7044GSI/Ariel JGK‐4’s as well as the surrounding support facilities for the plant. The initial plant was designed as a 140 MMscf/d facility. The permitting, design, engineering, procurement, construction, commissioning and startup were all managed by GCC.

Action

Challenges encountered on this project included the client replacing five (5) Waukesha 7044GSI’s with 1980 vintage Waukesha 9390GSI’s. This replacement resulted in multiple revisions: redesigned plot plans, additional power and backup requirements for the electric driven VFD coolers, structural design changes for the concrete foundation for the 9390, skid piping modifications to extend the coolers 15 ft beyond the skid design and building design changes. Further challenges in‐ cluded discarding the original plot plan and redesigning the site size several times in order to accommodate rock blasting on the mountain side. Reduction in the site space from a six acre site to a site of less than four acres (with an irregular shape) was also an issue.

GCC consistently managed all changes while developing BOM’s and AFE’s; and is‐ sued RFQ’s for all equipment, piping and materials. The GCC management team was utilized to over‐see equipment design and quality control for equipment sup‐ pliers and contractors.

We were awarded the contract in February 2013, with ground broken on the first station on May 1, 2013. The first station start‐up was November 15, 2013, after delays to rebuild the roadway in order to handle the larger size and weight of the 9390 skids.

Result

GCC was on‐hand during the start‐up of the facility which encountered no delays. Upon finalizing the project, we supplied the client with all P&ID’s, ISO’s, as‐builts, job books, daily operator form documents, as well as completed plant operation proce‐ dures for the facility and equipment.

GCC INC.
10200 E. Girard Avenue
SUITE B-410
DENVER, COLORADO 80231
303.400.4300 MAIN OFFICE
WWW.GCCINC.US

For more information contact:

Wayne Sartori
303.378.7911 Mobile
303.325.2100 Office
wsartori@gccinc.us